The Texas power grid is being rebuilt in real time. Energy Capital covers the policy fights, market mechanics, and technical decisions shaping what comes next. Hosted by Josh Rhodes (UT Austin) and Matt Boms (TAEBA), with the policymakers, regulators, and researchers at the center of it. Produced by ClarityForge Studios. Topics include ERCOT market operations, grid reliability, renewable integration, distributed energy resources, interconnection and transmission planning, regulatory economics, energy storage, demand response, and the Texas electricity market.

Episodes

What the Sierra Club wants from the Texas grid
What the Sierra Club wants from the Texas grid Aug 12, 2026 2653 Last month the Public Utility Commission of Texas held public hearings on plans to build giant 765 kilovolt transmission lines. The controversial plan drew complaints from influential voices, including Senate Business and Commerce Chairman Charles Schwertner, who asked commissioners to deny the pending applications for the lines in a letter. Cyrus Reed sat through the roughly 15 hours of testimony
How linear generators can fit into the Texas grid
How linear generators can fit into the Texas grid Aug 5, 2026 2186 Wind, solar, and storage are the only new categories of generation to reach the US power system at scale in fifty years. Craig Gordon thinks his company is adding one. Mainspring Energy’s linear generator drives magnets through copper coils rather than burning fuel in a flame, switches between natural gas, biogas, propane, and hydrogen under load, and ramps from minimum to full output in 25 second
Ten gigawatts are parked in American driveways
Ten gigawatts are parked in American driveways Jul 29, 2026 2362 About 6 million electric vehicles are on American roads, and roughly 1 million of them can already export power back to the grid. A typical one sits parked about 95 percent of the day, plugged in for 12 to 14 hours while needing 2 to 3 hours of charge. Texas still meets most of that capacity as load.That works out to roughly 10 gigawatts of export capacity. In ERCOT the value of tapping it splits
Wind is keeping West Texas ranches solvent
Wind is keeping West Texas ranches solvent Jul 22, 2026 2718 Cattle prices swing, goat prices swing, and the drought comes whether or not the ranch can afford it. For a fifth-generation West Texas operation, the search for income that holds steady through all of it comes from an unexpected source: the wind.A wind lease pays the same in a dry year as a wet one, creating a floor under an operation otherwise exposed to weather and commodity prices. When neighb
Why some large loads insist on paying their way
Why some large loads insist on paying their way Jul 15, 2026 2416 Some of the largest electricity buyers in the world have a message for Texas: charge us. The Texas Energy Buyers Alliance was the first organization to propose that large loads pay transmission charges tied to their approved capacity. The idea is to protect other customers as the grid builds out.The scale explains why. ERCOT estimates up to 110 gigawatts of new large loads could seek to connect ov
Texas competes on everything except transmission
Texas competes on everything except transmission Jul 8, 2026 3023 Texas built a competitive retail electricity market: consumers choose among roughly a hundred providers, and generators build power plants at their own risk with no guaranteed return. Transmission, the high-voltage lines that move power from where it is made to where it is used, runs on a different model. One utility builds each line and recovers every cost from ratepayers, plus a return, on time
What batch zero settles and what it leaves open
What batch zero settles and what it leaves open Jul 1, 2026 2958 Batch zero stops being theoretical on July 11. That is the day ERCOT’s rule for connecting large new customers takes effect. The new policy replaces a process that involved studying each giant load independently, then ordering restudies when new giant loads joined the queue, leaving projects stuck in a serial loop. Two prior episodes of this show traced how the new rule was designed. This one asks
Why PJM is looking at the Texas grid
Why PJM is looking at the Texas grid Jun 24, 2026 2267 ERCOT made a choice years ago that most of the country is now reconsidering. Texas runs an energy-only market with no capacity payments, connects generation through connect-and-manage, sorts out delivery in dispatch, and pushes interconnection risk onto developers. That design is a big part of why Texas has added generation faster than any other U.S. grid.PJM, the operator for much of the eastern
Inside the PUC's Cost-Allocation Overhaul with PUC Chairman Gleeson
Inside the PUC's Cost-Allocation Overhaul with PUC Chairman Gleeson Jun 10, 2026 2597 Texas spent five years rebuilding its electrical grid based on the lessons of Winter Storm Uri. Now regulators face a harder question: who pays for the surge of large new customers trying to connect?The projections for electricity demand run far above what will actually get built, and hyperscalers want to power their data centers within 18 months, a pace much faster than the three-to-five years la
How will data centers pay for power?
How will data centers pay for power? Jun 3, 2026 2669 Right now, connecting a data center to the grid works like Texas hog season: no defined season, no bag limits, first-come-first-served, file as many interconnection requests as you want. Travis Kavulla’s recent essay in American Affairs argues the power industry needs something closer to deer season, with defined rounds, allocation rules, and prices that reflect what grid access actually costs.The
How Texas decides which data centers to connect
How Texas decides which data centers to connect May 27, 2026 2970 ERCOT now has roughly 445 gigawatts of large loads asking to connect to the Texas grid, a figure so large that Joshua Rhodes says it might as well be infinite, because the system cannot physically build for all of it.To sort real projects from speculative ones, ERCOT is launching a new screening process called batch zero, and stakeholders voted to advance it at last week’s Technical Advisory Commi
How Texas plans to serve ‘infinite demand’
How Texas plans to serve ‘infinite demand’ May 20, 2026 2583 Texas has spent decades building transmission to serve load growth. The pattern worked when growth rose steadily with new homes, oil and gas operations, and the gradual expansion of the state’s industrial base. It is being tested by a different kind of customer: data centers requesting interconnection at a scale that exceeds what the grid can physically deliver.Eric Goff, founder of Goff Policy an